Project proponent: Clean Air Action Corporation

TIST Program in Kenya, VCS 001

VCS 594 is a tree-planting project in Kenya’s TIST programme. Small Groups manage trees, local field teams measure them, and carbon accounting connects that work to credits. Participant rights, payments and tree products have their own evidence.

How the project works →

Loading selected images…

Issued61,903VCUs recorded
Retired61,853VCUs recorded
Active holdings50VCUs recorded
Institutions10reviewed cards
Documents35current Registry listings

Open this project's map and codebook editor →

People, trees and carbon

How this project works

The 28 April 2011 report covers 2004–2010 and describes the shared TIST process for VCS 594–597. Its programme totals and examples cannot automatically be assigned to VCS 594 alone.

  1. Choose, plant and care for trees

    Small Groups choose tree species, numbers and planting schedules. The report describes members maintaining trees and retaining rights to trees and their products.

    Planting choices and tree ownership · p. 34 ↗
  2. Count trees and measure growth

    Trained field workers called Quantifiers visit groves, record boundaries, count trees by species and age, and measure a sample of tree circumferences. Counts and measurements are different parts of the record.

    Field measurement procedure · p. 37 ↗
  3. Calculate carbon estimates

    The report describes how measurements and equations estimate tree carbon. Its separate forecasts compare modeled project growth with a modeled without-project baseline. Forecasts, monitored estimates and issued credits describe different stages.

    Carbon calculation and baseline · pp. 35–39 ↗Separate forecasts and baseline · pp. 31–32 ↗
  4. Follow verification and issuance separately

    The project history keeps validation, verification and Registry issuance as distinct events. A forecast in a project report does not establish that credits were issued, sold or paid to a participant.

    Dated validation, verification and issuance records →Issued credits and retirements →

Rights and benefits have separate records

The public 2008 agreement template assigns carbon rights to Clean Air Action Corporation (CAAC). It documents tree-payment terms, a conditional revenue share and retained tree-product rights.

Later reports describe programme payments, and AENOR judged reported benefits credible within its review. Cash, products used and modeled values keep their own evidence; issuing a credit does not by itself establish a household payment.

Agreement terms and comments →Reported benefits and independent review →Funding and payment records →

The labels in the record

ARR, the project-type label, is short for afforestation, reforestation and revegetation.

AR-AMS0001 is the carbon-accounting methodology named in the 2011 report, which cites Version 05. The project type and the accounting method are different labels.

Historical method citation · p. 31 ↗What has been checked ↓
Reading, calculations and interpretation

What has been checked

Project report

Read in full

The 58-page 2011 implementation report has been read. Referenced methods and workbooks require their own checks.

2011 implementation report ↗
Carbon methodology

Full Version 05 check open

The report’s Version 05 citation is established. A verified full copy is still needed for the method review; the held Version 06 is a different edition. Applicability has not been determined.

Report’s method citation · p. 7 ↗
Benefit arithmetic

Three headline figures reproduced

The existing benefit-workbook review checked all 12 worksheets and reproduces the three headline valuations. This is separate from tracing the project’s carbon workbook or establishing people’s outcomes.

Valuations, calculations and sources →
Benefit interpretation

Review continues

Survey populations, time periods, cash and in-kind values, and extrapolation assumptions still need to be interpreted together. A reproduced value is not a receipt showing that a household was paid.

Existing findings, provisional claims and comments →

What the public record says about this project.

Start with the project identity. Then follow the institutions, credits, reported money terms, benefits, documents, and dated events back to their sources.

FPIC, Rights & Contracts

Participant consent, retained rights and agreements with CAAC. Staff and contractor arrangements remain separately identified.

FPIC, Rights & Contracts
100%

Participant rights and payment terms · 2008 public agreement; staff and contractor arrangements · separately dated records. Consent procedures and sampled checks are shown below with their sources.

Money · payment, remuneration and allocation termsControl of carbon rightsEmployment and contractor agreementsSolid · written terms or reported arrangementsDotted · 2011 reported allocation

The 2008 form names CAAC, the Small Group and each signing individual. Staff employment and Quantifier contractor agreements are separate arrangements. Public forms are not records of individual signatures.

  1. Individual Members → Small GroupsJoin other individuals to create Small Groups
  2. CAAC → Kenya StaffProvides employment contracts
  3. CAAC → QuantifiersIndependent contractor agreement
  4. Small Groups → CAACAssign group-held carbon-credit rights
  5. Individual Members → CAACAssign member-held carbon-credit rights
  6. CAAC → Small GroupsPay at least KSh 1.5 / live tree / year
  7. CAAC → Small GroupsShare 70% of positive net revenue · stock-weighted
  8. Small Groups → Individual MembersDecide members’ revenue allocation
  9. CAAC → Kenya StaffStaff salary terms
  10. CAAC → QuantifiersContractor remuneration terms
Community Organisation

Brown connects only the individual to retained assets (§2) and land or existing land-use rights (§4) in the 2008 terms. The grey community outline does not mean shared ownership. Assets · 2008 §2 ↗ Land or use rights · §4 ↗ Photo: Ladiar kinairi · seedlings · 11 April 2024 ↗

What the reviewed records establish about joining, understanding and signing.

Reported procedure

Training and understanding

The membership application procedure requires contract training and a comprehension check during the interview and site visit. The 2005 agreement also requires groups to sign that they have read, understood and agreed to updated certification requirements.

Scope and supporting records

These are affirmative procedures. The undated public application form is not a completed application or a participant-level record of understanding. The form does not identify the edition of the GHG contract supplied with the application.

Membership form · registration item 8 and final interview/site-visit item ↗2005 agreement · §7 ↗
Reported practice

Choices and unresolved grove disputes

The 2020 CCB-001 monitoring report describes voluntary joining, choices over trees and activities, and release from the contract and programme where a grove-ownership dispute cannot be resolved. The same report states that land tenure is by registered deed, while members attest to ownership and/or a right to use the land. It acknowledges disputes between farmers or family members.

Scope and supporting records

These are the proponent’s reported practices, not independent title checks or individual dispute records. The release pathway does not rewrite either contract into a general, unconditional withdrawal clause or establish how many disputes arose or how each ended.

2020 monitoring report · File 51941 · p. 31 · §§2.5.2–2.5.3 ↗Separately dated grievance routes ↗
Sampled verifier checks

Contracts checked with signatories

AENOR’s CCB-001 report says it reviewed interviewed members’ contracts and cross-checked the information with each signatory. Its interview findings also support understanding of risks and benefits within the sample.

Scope and supporting records

This is independent sampled assurance across the CCB-001 account associated with VCS 594. It is not a census of all participants or a ledger of completed payments.

AENOR · File 51942 · p. 20 · §4.3.10 ↗Sampled understanding · p. 16 ↗

Open questions: which version each participant signed, when they received and understood the terms, and individual withdrawal or dispute outcomes. The separate VCS 2338 findings remain in the related-project reference below.

Grievance routes and the 2017 policy →
Historical forms and participation records

The main map combines separately identified contract records. The participant terms use the 2008 form; the 2011 account reports both 2005 and 2008 forms as operational. These earlier forms, comparisons and participation records are retained as references; choosing a year here does not change the map.

FPIC, rights and agreements · 2005 / 2008

What the forms ask of participants

Six comparisons of rights, duties and choices. The 2011 report says both forms remained operational; an individual’s signing date and contract version require their own record.

2005 and 2008 agreement summaries, changes and retained terms. Open each topic for the complete conditions and source clauses.
Participant question
CAACSmall GroupIndividual participants
CAACSmall GroupIndividual participants
Changed and retained

Group and CAAC named; members sign individually and collectively. Trees, products and sustainable-agriculture crops belong to the group.

2005 original clauses ↗

Individual signers explicitly named. Retained assets belong to the member; stoves are included.

2008 original clauses ↗

ChangedIndividual role and ownership wording

RetainedIndividual signatures; retained trees and products

$0.02 per live tree per year for the first 20 years, conditional on good standing.

2005 original clauses ↗

Minimum 1.5 KSh per live tree per year, conditional on compliance. No 20-year cutoff in this clause.

2008 original clauses ↗

ChangedPrinted rate, currency wording and conditions

RetainedSeparate from the 70% share

After 20 years: 70% of the annual net value of the group’s own credits, using the stated price and cost basis.

2005 original clauses ↗

70% of TIST Kenya net revenue: first on a positive cumulative basis, then annually. Both use carbon-stock shares; losses must be offset before revenue shares resume.

2008 original clauses ↗

ChangedTiming and group-to-programme calculation

RetainedCosts deducted before the share

Quantification access; groups sign updated requirements as read, understood and agreed through certification issued at most annually.

2005 original clauses ↗

Broader CAAC information, training and own-account access duties. The earlier signed-certification clause is not repeated.

2008 original clauses ↗

ChangedExpanded duties; different update procedure

RetainedAccess to quantification information

60-year agreement. Plant at least 1,000 trees each year and raise them to maturity; replace dead trees annually for 20 years.

2005 original clauses ↗

60-year agreement. Plant at least 1,000 trees yearly for at least five years; maintain trees at least 30 years; replace dead trees annually for 20 years.

2008 original clauses ↗

ChangedPlanting, maintenance and other work duties

Retained60-year term; 20-year replacement duty

CAAC may cancel at any time. The group has an overdue-payment notice and cancellation route.

2005 original clauses ↗

CAAC’s stated grounds are beyond its control, including lack of a market, with 90 days’ notice. The group’s payment-default route largely remains.

2008 original clauses ↗

ChangedCAAC cancellation grounds and notice

RetainedGroup payment-default route; unpaid-credit rights revert

These are written terms. The 2005 “$” does not name a currency; the two rates do not establish a real increase. The 70% terms use net values after costs and have different triggers and allocation rules. Neither form supplies a dedicated grievance ladder or unconditional individual withdrawal. Open each topic for its full clauses and conditions.

Back to map selector ↑
Registry identity

VCS 594 · Late to Verify

Observed in the Verra registry

Project type

Afforestation, Reforestation and Revegetation (ARR)

1 source-bound classification receipt(s)

Methodology

AR-AMS0001

Source review needed

Project proponent as filed

Clean Air Action Corporation

Verra project-detail profile captured 9 Aug 2026 · 1 separately human-tagged filed-role card retained in Institutions

Evidence limits

What the record does not yet establish

exact registry profile fieldsnot observed in pinned exact profile excerpts

No exact retained profile excerpt supplies proponent, sectoral scope, methodology, or estimated annual quantity for this record.

methodologynot observed exactly and no filename token candidate

Methodology remains a source-acquisition task; no value is inferred from project type.

current certification statusnot asserted from document family presence

VCS identity and any CCB/sustainable-development filings are inventoried, but current certification or rider status is not inferred.

legal project boundary geometrynot included or inferred

Sensitive or legal geometry remains withheld; coarsened map decisions do not establish legal boundaries.

buyer seller price payment and benefit deliverynot inferred

Retirement labels, finance candidates, and filed benefit statements remain separate evidence objects.