Project → review → issued units

How a project
becomes credits.

Choose a programme. Follow the applicant, the documents, the assessor and the decision that creates the units.

Programme procedure · reviewed guidance, 2026-10-14

Verra Verified Carbon Standard

These boxes explain the procedure. A project’s actual approval and issuance need their own dated documents and registry events.

VCS 5.0 with exact effective-date table; earlier project/period editions remain relevant.

Jump to the process map ↓
Start here

Who applies—and what do they need?

Project proponent or duly authorized representative

Apply for the registry account, establish the project proponent and authorized signatory, and select an eligible VCS activity and methodology before submitting the project description.

The process allows a market participant to apply before validation. It does not establish every natural-person or unincorporated-group account eligibility rule. The proponent must show rights to operate and to the reductions/removals.

Land ownership, project representation, carbon title and beneficiary status are different roles; CCB and SD VISta are separately selected facets.

Documents to assemble

  • Account application and signatory/representation evidence
  • Right-to-operate and carbon-rights documents
  • Methodology/version applicability and project description
  • Baseline/additionality, monitoring plan, stakeholder and safeguard records
Applicant rule and clause

Registration and Issuance Process ↗
Edition 5.0 · §§1.1.3,2,3

VCS Standard ↗
Edition 5.0 · §§2.1,3.4–3.6,3.12–3.18

Types marked conditional require the named proponent/coordinator/holder role, rights, agreement and account approval. Not established is an evidence gap, not ineligibility.

Before design approval

Propose and establish

Eligible method, baseline/additionality, monitoring plan, rights and safeguards. Where the benefit-sharing rule applies, jointly design the mechanism with affected rights holders and specify form, allocation and timing. CCB causal impact logic belongs to the chosen CCB facet.

Before verified issuance

Monitor and demonstrate

Verified mitigation and required monitoring-period SDG reporting. VCS 5.0 §3.16 quantifies at least three SDGs or uses concurrent CCB/SD VISta verification. Required benefit sharing is assessed against applicable rights-holder conditions and the agreed schedule.

VVB assessment addresses the declared standard, method, period and claim. A carbon opinion, SDG claim or sampled community interview is not a census of cash receipt.

Under §3.16.2, the concurrent CCB/SD VISta verification alternative also requires documentation of contributions to at least three SDGs for the monitoring period.

Development goals are a separate requirement

Which goals must the project demonstrate?

A required SDG contribution, a voluntary label and a theory of change are different tests. The selected edition and product determine which applies.

Development goalsRequired in this edition

Quantify contributions to at least three SDGs for the monitoring period, or complete concurrent CCB/SD VISta verification.

Under §3.16.2, the concurrent CCB/SD VISta verification alternative also requires documentation of contributions to at least three SDGs for the monitoring period.

Requirement source and clause

VCS Standard ↗
Edition 5.0 · §3.16.2, physical p48

VCS Standard ↗
Edition 5.0 · §3.16.2, physical p48

Development goalsDepends on the route or condition

The SDG reporting update is effective immediately; this is separate from delayed stakeholder and benefit-sharing changes.

Requirement source and clause

VCS Version 5 overview and effective dates ↗
Edition September 10 2026 update · V5#18, physical p11

Causal logic / theory of changeDepends on the route or condition

CCB requires causal links from activities to expected outputs, outcomes and impacts; its footnote recommends a theory-of-change analysis.

When it applies: Only when pursuing the applicable CCB certification; not a universal VCS-only ToC requirement

Requirement source and clause

Climate, Community & Biodiversity Standards ↗
Edition 3.1 · G1.7 and footnote 25, physical p13

Causal logic / theory of changeRequired in this edition

Explain causal links between activities and expected outputs, outcomes and impacts.

When it applies: Applicable CCB certification route selected

Separate certification: Climate, Community & Biodiversity Standards. It does not create another originating carbon registry.

Requirement source and clause

Climate, Community & Biodiversity Standards ↗
Edition 3.1 · G1.7

Causal logic / theory of changeOptional / recommended

The G1.7 footnote recommends a theory-of-change analysis; distinguish this recommendation from mandatory causal links.

When it applies: Applicable CCB certification route selected

Separate certification: Climate, Community & Biodiversity Standards. It does not create another originating carbon registry.

Requirement source and clause

Climate, Community & Biodiversity Standards ↗
Edition 3.1 · G1.7 footnote25

Additional certificationOptional / recommended

Gold Level criteria are additional chosen distinctions, assessed within their particular scope.

When it applies: Applicable CCB certification route selected

Separate certification: Climate, Community & Biodiversity Standards. It does not create another originating carbon registry.

Requirement source and clause

Climate, Community & Biodiversity Standards ↗
Edition 3.1 · GL1–GL3

Required by the rulesChosen in project designMonitored indicatorAssessor’s finding

Project-selected SDGs, targets and evidence are being joined to the project catalog. A programme requirement does not identify a particular project’s chosen goals or establish delivery to a recipient.

Carbon method, safeguards, rights and benefit-sharing rules
Carbon accountingRequired in this edition

Apply an eligible methodology and monitoring plan; record method deviations separately.

VCS Standard ↗
Edition 5.0 · §§3.1, 3.15, 3.19

Community rights and benefit sharingDepends on the route or condition

Affected rights holders or customary rights holders/IPs trigger joint benefit-sharing design and implementation; cash or in-kind benefits and distribution schedules must be specified.

When it applies: Rights-holder conditions in §3.17.12

VCS Standard ↗
Edition 5.0 · §§3.17.12–3.17.16, physical pp54–55

Community rights and benefit sharingDepends on the route or condition

New benefit-sharing requirements apply to projects starting on/after 1 January 2027; existing projects enter at specified renewal or baseline-reassessment requests from 1 January 2030.

VCS Version 5 overview and effective dates ↗
Edition September 10 2026 update · V5#58, physical p8

SafeguardsRequired in this edition

Assess environmental, social and governance risks and stakeholder engagement under the applicable edition.

VCS Standard ↗
Edition 5.0 · §§3.17–3.18

Follow the project process

Applicant / operatorAssessment / programme reviewIssued units
  1. 01

    Opening a Verra Registry Account

    Market participant / Verra

    Apply for a registry account; Verra reviews and approves it. A validated project or purchase agreement is not required to apply.

    signup
    What the applicant prepares
    • Confirm the named account/participant role and submit the required identity, authority and agreement documents.

    Use only the applicable native route, product, edition and period; actions are a working checklist, not additional normative requirements.

    Source and clause

    Registration and Issuance Process ↗
    Edition 5.0 · §2, physical p5

  2. 02

    Pipeline Listing Process

    Project proponent / Verra

    Submit the required project information for listing as under development or under validation; follow the applicable public-comment route. Listing precedes registration.

    eligibilitydesign
    What the applicant prepares
    • Demonstrate eligibility for the selected activity, product and applicable rule editions.
    • Prepare the design package, baseline/additionality, monitoring plan and applicable consultation, safeguards and development-impact evidence.

    Use only the applicable native route, product, edition and period; actions are a working checklist, not additional normative requirements.

    Source and clause

    Registration and Issuance Process ↗
    Edition 5.0 · §3, physical pp6-11

  3. 03

    Project Validation and Verification

    Approved VVB / project proponent

    VVB assesses project design for validation and monitored reductions or removals for verification. These are different assessments, even when submitted together.

    validationmonitoringverification
    What the applicant prepares
    • Arrange the required independent or expressly permitted design assessment; answer findings and retain the final design opinion.
    • Implement the applicable monitoring plan for the actual period and keep supporting records separate from forecasts.
    • Submit period evidence for the required assurance route; resolve findings and retain the opinion’s scope and limitations.

    Use only the applicable native route, product, edition and period; actions are a working checklist, not additional normative requirements.

    Source and clause

    Registration and Issuance Process ↗
    Edition 5.0 · §4.1, physical pp12-14

  4. 04

    Registration and Verification Review

    Project proponent or authorized rights holder

    Request registration after validation; a registration request can precede first verification. Supply the documents required for the selected request.

    registration
    What the applicant prepares
    • Submit the native listing/registration package and retain the programme decision with its exact status.

    Use only the applicable native route, product, edition and period; actions are a working checklist, not additional normative requirements.

    Source and clause

    Registration and Issuance Process ↗
    Edition 5.0 · §4.2, physical pp14-17

  5. 05

    Project Review

    Verra

    Verra reviews the submission and resolves findings before registration or verification approval. A VVB report is not itself Verra approval.

    issuer decision
    What the applicant prepares
    • Respond to programme review and retain its decision separately from independent assurance.

    Use only the applicable native route, product, edition and period; actions are a working checklist, not additional normative requirements.

    Source and clause

    Registration and Issuance Process ↗
    Edition 5.0 · §4.3, physical pp18-21

  6. 06

    Project Registration and Initial VCU Issuance

    Verra Registry

    Following the applicable approvals, the registry creates VCU records and serials; the issuance levy must be paid before deposit. An approved verification volume can be issued incrementally.

    registrationissuance
    What the applicant prepares
    • Submit the native listing/registration package and retain the programme decision with its exact status.
    • Request the eligible product and retain the actual completed issuance event; an approval or estimate alone is insufficient.

    Use only the applicable native route, product, edition and period; actions are a working checklist, not additional normative requirements.

    Source and clause

    Registration and Issuance Process ↗
    Edition 5.0 · §4.4, physical pp22-24

  7. 07

    Periodic VCU Issuance

    Project proponent / VVB / Verra

    Subsequent monitored periods return through verification and approval before further issuance.

    monitoringverificationissuer decisionissuance
    What the applicant prepares
    • Implement the applicable monitoring plan for the actual period and keep supporting records separate from forecasts.
    • Submit period evidence for the required assurance route; resolve findings and retain the opinion’s scope and limitations.
    • Respond to programme review and retain its decision separately from independent assurance.
    • Request the eligible product and retain the actual completed issuance event; an approval or estimate alone is insufficient.

    Use only the applicable native route, product, edition and period; actions are a working checklist, not additional normative requirements.

    Source and clause

    Registration and Issuance Process ↗
    Edition 5.0 · §4.5, physical pp24-26

  8. 08

    VCU Retirements and Cancellations

    Registry account holder / Verra Registry

    The account holder initiates retirement of selected active VCUs; registry records distinguish retirement from cancellation.

    retirement
    What the applicant prepares
    • Check product-use eligibility and retain the completed retirement/cancellation record and named purpose or beneficiary.

    Use only the applicable native route, product, edition and period; actions are a working checklist, not additional normative requirements.

    Source and clause

    Registration and Issuance Process ↗
    Edition 5.0 · §4.6, physical pp26-27

Source-informed display order of functions, not a universal dependency chain. Use branch/pathway and ordering notes; repeated and combined assessments are possible.

What changes between programmes?

Pipeline listing is a disclosure gate. Registration requires the applicable validation/review route; validation and verification may be combined.

  • This is an edition-bound v5.0 process map, not a replacement for a historic v4 project workflow.
  • The retained listing still identifies v4.6 as active until 2027-01-01. Applicability and later clarifications require a project-specific check.
  • Registration may occur without initial issuance; approved verification quantity and issued quantity may differ.
  • V5#18 SDG reporting is immediately effective; V5#58 benefit sharing has specified 2027 new-start and 2030 existing-project triggers. Do not apply one effective date to all clauses.
  • Document identities: Registration and Issuance Process4.6 and VCS Standard4.7 are different documents; their version numbers do not conflict. Bind each document and its effective-date rules separately.

What still needs checking?

eligibility

partial

The process manual expressly defers technical eligibility to the VCS Standard, applicable methodology and related rules; no complete eligibility checklist is exported.

monitoring

partial

Monitoring report is an input to verification; detailed monitoring requirements are outside this process manual.

transfer

not detailed in retained sources

Trading is mentioned in account requirements; a standalone transfer procedure is not mapped in retained material.

These are gaps in this procedure guide. Completing a particular project requires its own evidence.

Rules behind this map

Registration and Issuance Process ↗

Edition 5.0 · 2025-12-16

Edition-specific description, not a claim that v5 applies to every October 2026 or historical project. Retained programme page also lists v4.6 active until 2027-01-01 and a 2026-06-09 clarification for v5; neither the v4.6 body nor that clarification is mapped here. Retained evidence reused on 2026-10-13; no live refresh. Publication date, capture date and applicability are distinct.
VCS programme document listing ↗

Edition not established · Publication date not established

Documents listing corroborates edition coexistence; no blanket effective-date inference. Retained evidence reused on 2026-10-13; no live refresh. Publication date, capture date and applicability are distinct.
VCS Standard ↗

Edition 5.0 · 2025-12-16 · Checked 2026-10-13

Read with the dated effective-date table and applicable corrections. v4.7 remains listed through 2026; no blanket historical replacement. Selected relevant primary-source sections through web retrieval; not whole-document QA
VCS Version 5 overview and effective dates ↗

Edition September 10 2026 update · 2026-09-10 · Checked 2026-10-13

Version-specific normative evidence; does not establish applicability to any Kenyan project or monitoring period. Selected relevant primary-source sections through web retrieval; not whole-document QA
Climate, Community & Biodiversity Standards ↗

Edition 3.1 · 2017-06-21 · Checked 2026-10-13

Official landing gives issue date; PDF title metadata contains 26OCT2016. Optional certification facet relative to VCS; bind actual CCB edition, including legacy v2. Selected relevant primary-source sections through web retrieval; not whole-document QA
VCS Standard ↗

Edition 5.0 · 2025-12-16 · Checked 2026-10-14

Publication date and access date differ; applicable methodology, corrections and transition rules still need a project-specific decision. Selected applicant, design, SDG, assurance or label sections; not whole-rulebook QA.
Climate, Community & Biodiversity Standards ↗

Edition 3.1 · 2017-06-21 · Checked 2026-10-14

CCB 2024 corrections and programme clarifications remain additional applicability checks. Selected applicant, design, SDG, assurance or label sections; not whole-rulebook QA.